The unit is rated for an operating temperature range of -30 to 50 °C, so it must be selected only for applications within this window.
Defines the process temperature envelope the cooler can support.
Source
“Operating temperature range -30...50 °C”
| Parameter | DC30 |
|---|---|
| Operating temperature range | -30...50 °C |
| Safety classification | I / NFL |
| Cooling power at 15°C | 0,2 kW |
| Cooling power at 0°C | 0,15 kW |
| Cooling power at -20°C | 0,07 kW |
| Refrigeration machine | air-cooled, natural refrigerant |
| Refrigerant (ASHRAE, GHS) | R-290 (A3, H220) |
| Global Warming Potential (GWP) | 0,02 |
| Refrigerant quantity | 0,05 kg |
| fluid connection | M16x1 male |
| Overall dimensions WxDxH ** | 190x250x360 mm |
| Net weight | 16 kg |
| Power supply requirement | 220-240V 1~/2~ 50/60Hz |
| max. current | 1,4 A |
| Fuse | 2 A |
| min. Fuse | 10A |
| max. Fuse | 16A |
| Degree of Protection | IP20 |
| min. ambient temperature | 5 °C |
| max. ambient temperature | 40 °C |
| from Serial-No. | 404196 |
** Please respect space requirements. See operating conditions at www.huber-online.com
The unit is rated for an operating temperature range of -30 to 50 °C, so it must be selected only for applications within this window.
Defines the process temperature envelope the cooler can support.
“Operating temperature range -30...50 °C”
Cooling capacity drops as the evaporating temperature falls, from 0.2 kW at 15 °C to 0.07 kW at -20 °C, so sizing must use the capacity at the actual operating point.
Prevents oversizing or undersizing based on a single nominal capacity figure.
“Cooling power at 15°C 0,2 kW at 0°C 0,15 kW at -20°C 0,07 kW”
The refrigerant is R-290 (propane, A3, H220) with a charge of 0.05 kg, so the installation area must be assessed for flammable refrigerant handling and ignition sources.
A3 refrigerant classification imposes ventilation and ignition-source restrictions on the installation site.
“Refrigerant (ASHRAE, GHS) R-290 (A3, H220)”
The fluid connection is M16x1 male, so mating hoses and fittings must match this thread.
Determines the hose and connector selection for the cooling circuit.
“fluid connection M16x1 male”
The unit requires 220-240 V single/two-phase 50/60 Hz supply with max current 1.4 A, so the electrical supply and protection must be sized accordingly.
Needed to confirm site power availability and breaker sizing.
“Power supply requirement 220-240V 1~/2~ 50/60Hz max. current 1,4 A”
The device is IP20, so it must be installed in a dry, protected location and not exposed to water or dust ingress.
Restricts the acceptable installation environment.
“Degree of Protection IP20”
The ambient temperature must stay between 5 °C and 40 °C, so the room conditions must be verified before commissioning.
Operation outside this range may reduce cooling capacity or damage the unit.
“min. ambient temperature 5 °C max. ambient temperature 40 °C”
Cooling capacity figures are valid at 20 °C room temperature and may drop if ambient rises, so capacity must be derated for warmer rooms.
Prevents assuming nominal capacity in non-20 °C environments.
“Output data valid for: Room temperature 20°C. If the ambient temperature rises, the cooling capacity may drop.”
Voltage tolerance is ±5% only with simultaneous frequency tolerance of ±2%, and combinations such as -5% voltage with +2% frequency are not allowed.
Defines acceptable supply quality and warns against certain combined deviations.
“Voltage + / - 5% with a simultaneous frequency tolerance of + / - 2%”
The equipment is EMC Class A, Group 1 to EN55011, so it may cause radio interference in residential areas and is intended for industrial environments.
Affects installation location and EMC compatibility with nearby sensitive equipment.
“Classification (disturbance) to EN55011: Class A, Group 1”
Single/two-phase devices are delivered with a power cable and country-specific plug that must be specified at ordering.
Ensures the correct plug type is supplied for the destination country.
“Single / two-phase devices (100V to 240V) --> with power cable and country-specific plug (please specify when ordering)”
Space requirements must be respected around the unit, so clearance must be planned according to the operating conditions.
Insufficient clearance can impair air-cooled condenser performance and service access.
“Please respect space requirements. See operating conditions at www.huber-online.com”