Rev x open combination kjeldahl systems user manual
Technical Reference Summary
Covered Models & Document Scope
This manual covers Labconco Open Combination (Macro) Kjeldahl Nitrogen Systems, models 21232 Series and 21233 Series, including the Six Place Open Combination Macro-Kjeldahl System (P/N 2123202). Electrical variants are identified by model suffix: -11 (115 V, single phase, 60 Hz), -12 (230 V, single phase, 60 Hz), and -13 (208/230 V, three phase, 60 Hz). Configurations include 6-place, 12-place, and 18-place heater racks; 12- and 18-place units use two or three 6-column distillation manifolds connected in series. The system comprises a lower digestion rack and an upper distillation rack and does not include an integral blower or safety enclosure.
Section-by-Section Technical Breakdown
The Open Combination (Macro) Kjeldahl System is intended for Total Nitrogen determination in feeds, grains, soils, fertilizers, plant tissue, water, organic wastes, and food products. It consists of a lower digestion rack and an upper distillation rack and uses macro-size glassware. Sample sizes up to 5 grams can be accommodated, but higher organic content requires smaller samples due to the vigorous digestion reaction.
- Designed for standardized (Macro) Kjeldahl Nitrogen Determination Methods.
- Sample sizes up to 5 grams are accommodated by the digestion/distillation flask size.
- Higher organic content in a sample type requires smaller sample sizes.
- The system is not enclosed; excess heat and personnel safety must be considered when selecting an installation location.
- AOAC and AACC published methods should be consulted for step-by-step analytical procedures.
The system uses 600-watt electric heaters in both the lower digestion and upper distillation racks, each regulated by an infinite control switch. The lower fume removal manifold is CPVC with heat-resistant PTFE nipples and orients flasks at 45 degrees to promote acid reflux. The acid fume piping exhaust system requires a remote blower and a 6-inch exhaust stack connected to leak-tight PVC ductwork venting 10 ft (3 meters) above the building roof.
- 600-watt heaters are used in both the lower digestion and upper distillation racks.
- Infinite control switches regulate each heater.
- The digestion heater assembly can be moved closer to or away from the acid fume removal manifold to accommodate different flask sizes.
- The lower fume removal manifold is CPVC with heat-resistant PTFE nipples extending into the flask opening.
- Flasks are oriented at a 45 degree angle to the fume removal manifold to promote condensation and refluxing during the 45+ minute digestion.
- The unit does NOT have an integral blower; exhaust piping must be connected to a remote blower.
- The 6-inch exhaust stack must connect to leak-tight PVC ductwork venting 10 ft (3 meters) above the building roof.
- Distillation cooling water temperature is indicated on a thermometer at the water outlet of the distillation manifold.
- Water connections are 3/4" NPT with a minimum 1/2" supply line.
- For ground water above 80°F (27°C), a recirculation water chiller system is required.
- Each 6-column distillation manifold has 3/4" NPT tap water inlet and outlets.
The system is shipped fully assembled and is heavy; it cannot be disassembled to reduce size, so special arrangements are needed for moving it to its final location. Exhaust ductwork, remote blower, electrical service, and water supply/drain connections should be completed by a licensed contractor. The system does not include a safety enclosure and should be installed away from normal laboratory personnel traffic, with spot exhaust ventilation recommended to remove excess heat.
- The system is shipped fully assembled.
- Exhaust ductwork, remote blower (if required), electrical service, water supply, and drain connections should be completed by a licensed contractor.
- The customer must purchase Kjeldahl flasks, one-hole rubber stoppers, and distillate receiving flasks.
- Connecting bulbs and delivery tubes are provided with each system.
- Levelers and distillation cooling water thermometers are shipped installed.
- The system is heavy and cannot be disassembled to reduce overall size.
- Special instruction tags must not be removed until installation is completed.
- The system does not include a safety enclosure; install segregated from normal laboratory personnel traffic.
- Spot exhaust ventilation is recommended at the final installation location to remove excess heat.
Systems are factory-wired per the model number ordered. Model suffixes -11, -12, and -13 designate 115 V single phase, 230 V single phase, and 208/230 V three phase respectively. Amperage requirements vary by number of heaters; a qualified electrician must connect the facility supply to the main breaker box and provide an earth ground. The remote blower can be wired to the unit's on/off switch and must be on before using the unit.
- Model ending -11: 115 V, single phase, 60 Hz.
- Model ending -12: 230 V, single phase, 60 Hz.
- Model ending -13: 208/230 V, three phase, 60 Hz.
- 6-PL -11: 65 amp; 12-PL and 18-PL -11: not listed.
- 6-PL -12: 35 amp; 12-PL -12: 66 amp; 18-PL -12: 96 amp.
- 6-PL -13: 20 amp; 12-PL -13: 38 amp; 18-PL -13: 56 amp.
- The remote blower can be wired to the on/off switch on the unit; the blower MUST be on before using the unit.
- An earth ground must be provided per code.
- Before applying power, check the electrical panel and breakers for loose connections.
The upper distillation rack uses individual condensation columns connected by a common manifold (6 columns per manifold). Tap water inlet and outlet connections are 3/4" NPT and the supply line should be minimum 1/2" ID to provide 6-8 gallons (23-30 liters) per minute through the condensation columns. The outlet plumbing must be free of back pressure, and discharged water is not acid contaminated so standard drain lines may be used.
- All plumbing connections and components must be free of foreign material before final connections.
- 6 columns per manifold; 12- and 18-heater systems use two or three 6-column manifolds connected in series.
- Tap water inlet and outlet connections are 3/4" NPT.
- Supply line should be minimum 1/2" ID.
- Required water flow through condensation columns: 6-8 gallons (23-30 liters) per minute.
- The outlet plumbing must be free of back pressure to avoid flow restriction.
- Water discharged from the distillation manifold is not acid contaminated; standard drain lines may be used.
The exhaust duct connection on top of the damper is sized for 6-inch nominal (6-5/8" O.D.) vent duct and is supplied with a short 6-inch PVC pipe and flexible coupling. All exhaust ductwork must be acid-resistant and sealed air-tight using only acid-resistant sealant. The bottom of the piping assembly has a condensate drain with corrosion-resistant tubing; condensate is concentrated acid and must be collected in a closed acid-proof container or plumbed to an acid-resistant drain.
- Exhaust duct connection is sized for 6-inch nominal (6-5/8" O.D.) vent duct.
- A short piece of 6-inch PVC pipe and a flexible coupling with clamps are supplied.
- The flexible coupling must be sealed air-tight to the exhaust ductwork.
- All exhaust ductwork must be acid-resistant and sealed air-tight.
- Use only acid-resistant sealant on ductwork joints.
- Condensate drain at the bottom of the piping assembly; condensate is concentrated acid.
- Condensate must be collected in a closed acid-proof container emptied regularly or plumbed to an acid-resistant drain line.
The required exhaust airflow is 25 CFM at an average airflow velocity of 117 feet per minute, measured 48 inches above the flexible coupling using a 6-point Pitot traverse per ANSI/ASHRAE 51-1999. If the remote blower pulls more than 25 CFM at the measurement point, the damper must be closed to reduce airflow to the recommended 25 CFM. PVC or fiberglass duct is recommended, and ductwork must be supported independently of the Kjeldahl system.
- Required airflow: 25 CFM.
- Average airflow velocity: 117 feet per minute.
- Measurement point: 48 inches above the flexible coupling.
- Test method: Pitot Traverse in Inlet Duct per ANSI/ASHRAE 51-1999, 6-point duct traverse pattern.
- If remote blower pulls more than 25 CFM at the measurement point, close the damper to reduce airflow to 25 CFM.
- PVC or fiberglass duct is recommended.
- Exhaust ductwork must be supported independent of the Kjeldahl system to avoid distortion of the piping assembly.
The digestion heaters are located in a stainless steel drip shield resistant to acid attack. Liquid acid spills can be drained to an acid-resistant container via the drip tube located on the left side of the digestion rack.
- Drip shield is constructed of stainless steel and is resistant to acid attack.
- Liquid acid spills can be drained to an acid-resistant container.
- Drip tube is located on the left side of the digestion rack.
The glassware installation figure shows the arrangement of the connecting bulb, rubber tubing, receiving flask, delivery tube, distillation manifold, and distillation flask. Connecting bulbs and delivery tubes are included with Macro Kjeldahl Systems.
- Connecting bulbs and delivery tubes are included with Macro Kjeldahl Systems.
- Components shown: connecting bulb, rubber tubing, receiving flask, delivery tube, distillation manifold, distillation flask.
The apparatus is designed for 500 or 800 ml Kjeldahl flasks, and the digestion heaters move forward or backward on the runway to accommodate either size. After turning on heat controllers, wait approximately 5 to 10 minutes for preheating. Start the acid fume removal blower or water aspirator and verify suction holds a 2" x 2" (51 mm x 51 mm) tissue paper over the nipple; begin cooling water and ensure its temperature does not exceed 80°F (27°C).
- Designed for 500 or 800 ml Kjeldahl flasks.
- Digestion heaters move forward or backward on the runway to accommodate either flask size.
- Wait approximately 5 to 10 minutes after turning on heat controllers to ensure proper preheating.
- Start the acid fume removal blower or water aspirator (depending on model).
- Suction should be sufficient to hold 2" x 2" (51 mm x 51 mm) tissue paper over the nipple on the digestion manifold.
- Cooling water temperature should not exceed 80°F (27°C).
- Regulate water flow with the control valve and watch the thermometer.
- Rinse inner stainless steel condensing tubes by boiling nitrogen-free water in Kjeldahl flasks attached to the condensation columns before commencing a distillation procedure.
Keeping the system clean preserves appearance and improves equipment life. Wash with a weak sodium hydroxide solution and rinse with clear water. Sulfate salt buildup between the channel support and fume removal manifold should be neutralized periodically with weak sodium hydroxide solution.
- Wash with a weak solution of sodium hydroxide and rinse with clear water.
- Sulfate may build up between the channel support and the fume removal manifold.
- Neutralize sulfate buildup periodically with a weak sodium hydroxide solution.
No suction pressure adjustment is required at the manifold when the blower exhaust system is used. The remote blower should be inspected annually for debris, proper operation, and adequate airflow. Reduced suction in the nipples due to obstruction can usually be cleared by boiling water in flasks on the digestion heaters with the remote blower running to draw steam through the fume pipe.
- No adjustment is required on the suction pressure at the manifold when the blower exhaust system is used.
- Inspect the remote blower annually for debris, proper operation, and adequate airflow.
- Reduced nipple suction is usually due to obstruction within the exhaust system.
- Clear obstructions by boiling water in flasks on the digestion heaters with the remote blower on to draw steam through the fume pipe.
The stainless steel drip shield resists most acid attack but acid spills can cause discoloration and marring unless cleaned promptly. Major acid spills should be washed down promptly, the surface cleaned periodically with residential stainless steel sink cleaning compound, and the bright appearance renewed by lightly sanding with 220 grade emery paper.
- Promptly wash down all major acid spills contained by the shield.
- Periodically clean the stainless surface with any residential stainless steel sink cleaning compound.
- After cleaning, renew bright appearance by lightly sanding with 220 grade emery paper.
Appendix A lists replacement parts for electrical heaters, motor/blower components, and miscellaneous items with part numbers and descriptions. Key heater parts include infinite heater controls for 115 V and 230 V, 600 W heater elements in packages of six, and PTFE nipples. Miscellaneous parts include distillation manifold, rubber condenser tubing, and a replacement fume pipe kit.
- Heater Control, Infinite (115 V): P/N 1315400.
- Heater Control, Infinite (230 V): P/N 1315500.
- Heater element, 115 V, 600 W (package of 6): P/N 2033100.
- Heater element, 230 V, 600 W (package of 6): P/N 2033200.
- PTFE nipple: P/N 2165800; plastic screws for PTFE nipple: P/N 1880128.
- Distillation manifold – 6 place stainless steel: P/N 2152402.
- Tubing, rubber condenser connecting, per foot: P/N 1620500.
- Kit, Replacement Fume Pipe: P/N 2078800.
- Assembly inlet & outlet manifold (12 unit only): P/N 2146400.
Appendix B provides dimension A and maximum heater power for the 6 Place Combo and 12 Place Combo models. The 6 Place Combo has dimension A of 41.8 inches and 7 kW maximum heater power; the 12 Place Combo has dimension A of 71.8 inches and 14 kW maximum heater power.
- 6 Place Combo: A = 41.8 inches, Heater Max = 7 kW.
- 12 Place Combo: A = 71.8 inches, Heater Max = 14 kW.
Appendix C provides a titrimetric Total Kjeldahl Nitrogen method for reference, covering digestion, distillation, and titration. The method uses 500-800 ml macro flasks, 600 W burners, and specifies reagents, sample sizes of 0.250-1.000 gram, and calculation formulas. It notes that some nitrogen compounds such as amines, nitro-compounds, hydrazones, oximes, semicarbazones, and some tertiary amines may not be converted.
- Method determines Total Kjeldahl Nitrogen (TKN) in water and organic substances.
- Three steps: digestion to convert organic nitrogen to ammonia, distillation to transfer ammonia to trapping solution, and titration.
- Some compounds containing nitrogen may not be converted: amines, nitro-compounds, hydrazones, oximes, semicarbazones, and some tertiary amines.
- Described for Macro-Size glassware (500-800 ml flasks).
- Preheated burners should bring 250 ml of water at 25°C to a rolling boil within 5 minutes.
- Condensation columns should cool distillate to 75°F (23.8°C).
- Sample size: 0.250-1.000 gram, weighed to nearest 0.1 mg/ml.
- Digestion reagents per flask: 20 ml sulfuric acid, 0.04 g CuSO4, 15 g K2SO4, 8-10 boiling stones.
- Total digestion time approximately 1 hour.
- Distillation: add 100 ml of 45% sodium hydroxide solution; distill >8-10 minutes.
- For nitrogen concentrations above 1 mg/l, titrimetric determination; below this, colorimetric or potentiometric methods recommended.
- Titration should require at least 15 ml of titrant to be accurate; record to nearest 0.05 ml.
- Protein factors: 5.7 for bread/wheat/wheat flour, 6.25 for other grains, 6.38 for milk, 6.25 for unknown source.
Key Integration, Operating & Safety Requirements
| Specification / Condition | Engineering Implication | Applies To |
|---|---|---|
| Sample sizes up to 5 grams can be accommodated due to the size of the digestion/distillation flasks. p.6 ↗ | Select this macro system for samples requiring up to 5 g; higher organic content requires smaller sample sizes due to vigorous digestion. | Open Combination (Macro) Kjeldahl Systems |
| 600-watt heaters are used in both the lower digestion and upper distillation racks. p.6 ↗ | Electrical supply must be sized for the total number of 600 W heaters per rack. | All models |
| The 6-inch exhaust stack must be connected to leak-tight PVC ductwork venting 10 ft (3 meters) above the building roof. p.7 ↗ | Ductwork routing must terminate at least 10 ft above the roof and be leak-tight. | All models |
| For facilities where ground water temperature exceeds 80°F (27°C), a recirculation water chiller system is required. p.7 ↗ | Verify site cooling water temperature; if above 80°F, include a chiller in the installation. | All models |
| Electrical requirements: -11 = 115 V single phase 60 Hz; -12 = 230 V single phase 60 Hz; -13 = 208/230 V three phase 60 Hz. p.10 ↗ | Order the correct model suffix for the facility electrical service. | All models |
| Amperage: 6-PL -11 = 65 A; 6-PL -12 = 35 A; 12-PL -12 = 66 A; 18-PL -12 = 96 A; 6-PL -13 = 20 A; 12-PL -13 = 38 A; 18-PL -13 = 56 A. p.10 ↗ | Size circuit breakers and supply wiring per the applicable model and heater count. | 6-PL, 12-PL, 18-PL variants |
| The remote blower MUST be on before using the unit. p.10 ↗ | Interlock or procedure must ensure blower operation before heaters are used. | All models |
| Tap water inlet and outlet connections are 3/4" NPT and the supply line should be minimum 1/2" ID. p.11 ↗ | Plumbing must provide at least 1/2" ID supply to meet flow requirements. | All models |
| Required water flow through condensation columns is 6-8 gallons (23-30 liters) per minute. p.11 ↗ | Verify facility water supply can deliver this flow rate to achieve sufficient condensation. | All models |
| Exhaust duct connection is sized for 6-inch nominal (6-5/8" O.D.) vent duct. p.12 ↗ | Ductwork must match 6-inch nominal size and be acid-resistant and air-tight. | All models |
| Required exhaust airflow is 25 CFM at an average velocity of 117 feet per minute, measured 48 inches above the flexible coupling. p.12 ↗ | Commission the remote blower and damper to achieve 25 CFM at the specified measurement point. | All models |
| If the remote blower pulls more than 25 CFM at the measurement point, close the damper to reduce airflow to 25 CFM. p.13 ↗ | Damper adjustment is required after blower installation to meet the specified airflow. | All models |
| The apparatus is designed for 500 or 800 ml Kjeldahl Flasks. p.15 ↗ | Purchase flasks in either 500 ml or 800 ml size; heaters adjust on the runway for either. | All models |
| Suction should be sufficient to hold 2" x 2" (51 mm x 51 mm) tissue paper over the nipple on the digestion manifold. p.15 ↗ | Use this as a field check for adequate fume removal suction. | All models |
| Cooling water temperature should not exceed 80°F (27°C). p.15 ↗ | Monitor thermometer at water outlet and regulate flow; use chiller if supply exceeds 80°F. | All models |
| Wait approximately 5 to 10 minutes after turning on heat controllers to ensure proper preheating. p.15 ↗ | Allow preheat time before starting digestion or distillation. | All models |
| 6 Place Combo: dimension A = 41.8 inches, heater max = 7 kW; 12 Place Combo: dimension A = 71.8 inches, heater max = 14 kW. p.19 ↗ | Use dimensions for bench/layout planning and verify electrical capacity for maximum heater power. | 6 Place Combo, 12 Place Combo |
| Preheated burners should bring 250 ml of water at 25°C to a rolling boil within 5 minutes; condensation columns should cool distillate to 75°F (23.8°C). p.21 ↗ | Use these performance criteria to verify heater and condenser function. | All models |
| Digestion reagents per flask: 20 ml sulfuric acid, 0.04 g CuSO4, 15 g K2SO4, 8-10 boiling stones; sample size 0.250-1.000 gram. p.21 ↗ | Follow these quantities for the reference TKN method. | All models |
| Distillation: add 100 ml of 45% sodium hydroxide solution and distill >8-10 minutes; receiving solution changes from purple to green. p.22 ↗ | Use color change and time as indicators of complete ammonia transfer. | All models |
Faults & Troubleshooting
| Code / Symptom | Possible Cause | Remedy | Note |
|---|---|---|---|
| Suction in the nipples is reduced p.16 ↗ | Obstruction within the exhaust system | Boil water in a number of flasks placed on the digestion heaters with the remote blower on and operating correctly to draw steam through the fume pipe and wash out the obstruction. | Exhaust Systems Maintenance |