  1. Overview p. 1
    Product introduction and general description of the CS 75-H bath
  2. Spec p. 2
    Technical data according to DIN 12876, including performance and dimensions
  3. p. 1 table, 32 rows

Technical data according to DIN 12876 — CS 75-H by Van der Heijden (Order-No.: VDH4100108)

ParameterValue
Operating temperature range-20...85 °C
temperature set point / displaycolour LED Touchscreen
Internal temperature sensorPt100
Temperature stability at -10°C0,5 K
Interface digitalRS232
Safety classificationI / NFL
Heating power3 kW
Cooling power at ambient temperature 20°C.
at 15°C9 kW
at 10°C7,5 kW
at 0°C5,5 kW
at -10°C3 kW
at -20°C2,4 kW
Refrigeration machineair-cooled, CFC- and HCFC-free
Refrigerant (ASHRAE, GHS)R-449A (A1, H280)
Refrigerant quantity4,5 kg
CO2 equivalent6,29 t
Circulation pump: max. delivery70 l/min
max. delivery pressure3,7 bar
Pump connectionG3/4 male
min. filling capacity160 l
max. filling capacity175 l
Overall dimensions WxDxH **800x850x1665 mm
Net weight275 kg
sound pressure level +/- 4 dB(A)66 dB(A)
Power supply (3 Phase)400V 3~ 50Hz
max. current (3 Phase)27 A
Fuse (3 phase)3x32A
Degree of ProtectionIP52
min. ambient temperature5 °C
max. ambient temperature32 °C
from Serial-No.:1.0/24

** Overall dimensions WxDxH

Engineering Facts

13 facts · every claim linked to a page
Installation

The chiller requires a three-phase 400 V supply with a 3x32 A fuse, so the site electrical infrastructure must be sized accordingly.

Determines the electrical connection, cable sizing and breaker rating needed at the installation site.

Source
“Power supply (3 Phase) 400V 3~ 50Hz”
Installation

Three-phase devices drawing less than 63 A are delivered with a cable but without a plug, so the customer must provide and fit the site plug.

Affects procurement and installation planning because the mating plug is not included.

Source
“Three-phase devices with current consumption less than 63A --> with cable, without plug”
Installation

The unit must be operated within an ambient temperature window of 5 to 32 °C, which constrains where it can be installed.

Room conditions at the installation site must be verified before commissioning.

Source
“min. ambient temperature 5 °C”
Performance

Cooling capacity is rated at 20 °C room temperature and drops if ambient temperature rises, so capacity must be derated for warmer rooms.

Prevents undersizing the chiller when the actual installation room is warmer than 20 °C.

Source
“Output data valid for: Room temperature 20°C. If the ambient temperature rises, the cooling capacity may drop.”
Installation

Voltage and frequency tolerances are coupled: a -5% voltage deviation is only allowed together with -2% frequency, not with +2%.

Site power quality must be checked against the combined tolerance rule, not voltage alone.

Source
“-5% voltage and +2% frequency -> not allowed!”
Operation

The flow rate is adjusted via a manual bypass valve on the rear of the chiller, so rear access is needed for balancing.

Installation layout must leave clearance at the rear for flow adjustment and service.

Source
“The flow rate can be adjusted via the manual bypass valve on the backside of the chiller.”
Safety

The refrigerant R-449A is classified A1 with GHS hazard H280, so refrigerant handling and ventilation precautions apply.

Affects site safety assessment and refrigerant handling procedures.

Source
“R-449A (A1, H280)”
Compliance

The equipment emits as Class A, Group 1 per EN55011, which is industrial EMC classification and may restrict use in residential environments.

Determines whether the chiller can be installed in an environment with residential EMC requirements.

Source
“Classification (disturbance) to EN55011: Class A, Group 1”
Operation

The recommended thermofluid is a 50:50 water-monoethylene glycol mixture, which sets the fluid to be filled at commissioning.

Guides fluid selection and prevents use of incompatible or freeze-unsafe media.

Source
“Recommended thermofluid: Water - Monoethylene Glycol 50:50”
Installation

The pump connection is G3/4 male, so mating hoses and fittings must match this thread.

Needed to specify connection hoses and adapters before delivery.

Source
“Pump connection G3/4 male”
Selection

The tank holds between 160 and 175 litres, which sets the required fluid volume and expansion allowance.

Determines the quantity of thermofluid to procure and the expansion volume to plan.

Source
“min. filling capacity 160 l”
Installation

The unit is IP52, so it is protected against dust and dripping water but not against water jets or immersion.

Constrains cleaning methods and placement in wet or washdown areas.

Source
“Degree of Protection IP52”
Maintenance

The condenser is air-cooled with a high-efficiency fan, so adequate air flow and cleaning access around the condenser are required.

Affects placement clearances and the maintenance plan for condenser cleaning.

Source
“Condenser in air-cooled design, performance- optimized by a built-in high-efficiency fan motor.”