Selection
The chiller is rated for an operating temperature range of -10 to 100 °C, so it must be matched to the process temperature window.
Defines whether the unit can cover the required process temperatures before selection.
Source
“Operating temperature range
-10...100 °C”
Performance
Cooling capacity drops from 7 kW at 15 °C to 2.3 kW at -10 °C, so the duty point must be checked at the actual operating temperature.
Prevents oversizing or undersizing when the process runs at low temperature.
Source
“at 15°C
7 kW
at 0°C
4 kW
at -10°C
2,3 kW”
Installation
The unit requires a 400 V three-phase 50 Hz supply, so site power must be verified before installation.
Determines electrical infrastructure and whether a suitable three-phase feed is available.
Source
“Power supply (3 Phase)
400V 3~ 50Hz”
Installation
Three-phase devices below 63 A are delivered with cable but without plug, so the customer must provide the final connection.
Affects electrical installation planning and who supplies the plug or terminal connection.
Source
“Three-phase devices with current consumption less than 63A --> with cable, without plug”
Installation
Voltage and frequency tolerances are ±5% and ±2% respectively but must not be combined in opposite directions, so supply quality must be checked.
Avoids invalid supply conditions that could damage the compressor or void compliance.
Source
“Voltage + / - 5% with a simultaneous frequency tolerance of + / - 2%”
Operation
The unit is rated for ambient temperatures from 5 to 40 °C, so the installation room must stay within this range.
Ambient conditions directly affect cooling performance and reliable operation.
Source
“min. ambient temperature
5 °C
max. ambient temperature
40 °C”
Performance
Cooling capacity is valid at 20 °C room temperature and may drop at higher ambient, so performance must be derated for warm rooms.
Prevents selecting a unit that cannot meet duty in a warm plant room.
Source
“Output data valid for: Room temperature 20°C. If the ambient temperature rises, the cooling capacity may drop.”
Installation
The unit is air-cooled, so adequate air flow and heat rejection space must be provided at the installation site.
Air-cooled units need ventilation and clearance, which affects room layout.
Source
“Refrigeration machine
air-cooled, CFC- and
HCFC-free”
Safety
The refrigerant is R-449A with GHS classification H280, so refrigerant handling and ventilation precautions apply.
Requires awareness of pressurized gas hazards during installation and service.
Source
“R-449A (A1, H280)”
Cumplimiento
The unit is classified Class A, Group 1 for electromagnetic disturbance, so it is intended for industrial environments.
Class A equipment may not be suitable for residential or light-commercial EMC environments.
Source
“Classification (disturbance) to EN55011: Class A, Group 1”
Installation
The degree of protection is IP20, so the unit must be installed in a dry, protected location.
Prevents installation in wet or dusty areas where ingress protection is required.
Source
“Degree of Protection
IP20”
Installation
The pump connection is G1 1/4 male, so mating hoses and fittings must match this thread.
Ensures correct hydraulic connection and avoids adapters or leaks.
Source
“Pump connection
G1 1/4 male”
Operation
The minimum filling capacity is 5 l and expansion volume is 7.5 l, so the external loop volume must be considered.
Affects heat transfer fluid charge and expansion tank sizing for the application.
Source
“min. filling capacity
5 l
Volume of expansion
7,5 l”
Maintenance
The sound pressure level is 66 dB(A) ±4 dB(A), so acoustic planning may be needed in occupied areas.
Noise limits may dictate location or acoustic treatment.
Source
“sound pressure level +/- 4 dB(A)
66 dB(A)”