Prep SFC 150 MultiGram System Site Preparation Guide
Technical Reference Summary
Covered Models & Document Scope
Prep SFC 150 MultiGram System (MGM), document 715005746 VER. 03 (previously Rev. B). The system is available only as a 220-volt configuration using 6-20P plugs. The guide covers site preparation for the complete system including ABPR, CHILL (Julabo FL601 230 V/50 Hz or 230 V/60 Hz), COL (Torus 2-PIC OBD 5 µm 19 x 100 mm Prep Column), DET (2489 UV/Visible or 2998 PDA), FM1, GLS, HE1 (CPVC 20' 6 kpsi), HE2/HE3/HE4 (SFC 1000 W), MSI, P1 (P-200X), P2 (2545 Quaternary Gradient Module), P3, PCC, PFS, SS, TC, TRAY, and WASTE 2 L / 10 L / 20 L assemblies. Optional valves each require their own power receptacle on a common earthed source.
Section-by-Section Technical Breakdown
The system ships in two crates: a large crate containing the ABPR, collection cabinet, chiller, fraction selector, detector, GLS, heat exchangers HE2-HE4, P-200X pump, 2545 quaternary gradient module, make-up pump, modifier stream injector, and tray/risers; and a small crate containing the system shelf, temperature controller, flow meter, dampener, HE1, and chiller tubing. Crate dimensions are given, and lifting/moving rules require passageways and doorways to accommodate the largest container or unboxed component. Storage before installation must be 0 to 40 °C and <80% RH noncondensing.
- Large crate: 123.2 cm W x 106.6 cm D x 158.8 cm H (48.5 x 42 x 62.5 inches).
- Small crate: 114.3 cm W x 78.7 cm D x 77.5 cm H (45 x 31 x 30.5 inches).
- Keep shipping containers on the pallet; if transported individually, move all containers and retain packing slips.
- Do not bump or jolt the system during transport; use a forklift or trolley on uneven surfaces.
- Doorways must accommodate the largest unboxed component.
- Storage: 0 to 40 °C (32 to 104 °F), humidity <80% noncondensing, unopened crates.
The laboratory bench must support the weight of all components and provide at least 152 cm (5 ft) of vertical clearance. Recommended configurations require at least 15.2 cm (6.0 inches) between the collection cabinet and the shelf system, and waste containers and chiller may be placed below, behind, or in front of the shelf system. Component dimensions and weights are tabulated for all modules, and clearances specify 25.4 cm (10 inches) rear clearance for system components, CO2 cylinder within 152 cm (5 ft) of the rear of the system, and the Julabo chiller within 1 m (39.4 inches) of the CO2 pump.
- Minimum vertical clearance above the bench: 152 cm (5 ft).
- Minimum gap between collection cabinet and shelf system: 15.2 cm (6.0 inches).
- Rear clearance for system components: 25.4 cm (10 inches).
- CO2 cylinder must be within 152 cm (5 ft) of the rear of the system.
- Julabo chiller must be within 1 m (39.4 inches) of the CO2 pump.
- Heaviest listed component: CHILL at 48.2 kg (106 lb); P2 at 39.5 kg (87 lb); P1 at 38.1 kg (84 lb); PCC at 34 kg (75 lb).
The system requires clean, high-purity HPLC-grade solvents; failure to provide clean solvents and glassware can significantly delay installation. Methanol (4 L), ultra-pure water, and ethylene glycol must be available for installation. Contamination control guidance is referenced in Waters document 715001307 and product SDSs.
- Use HPLC-grade solvents only.
- Have 4 L methanol, ultra-pure water, and ethylene glycol available.
- Glassware must not be washed with detergent or in common dishwashing facilities; detergent residues (e.g., polyethylene glycol) and vinyl-coated steel racks can contaminate the system.
The system requires liquid CO2 at 99.97% purity (food-grade) or better. Supply may be a cylinder with dip tube capable of delivering a minimum of 55 bar, or an in-house distribution system with a clean, particle-free, non-lubricated shutoff valve free from silicone and EPDM rubber and compatible with CO2. Low-pressure cylinders such as dewars are not acceptable, and helium head-pressure CO2 cylinders must not be used to avoid retention time variation.
- CO2 purity: 99.97% minimum (food-grade or better).
- Minimum delivery pressure: 55 bar.
- Cylinder must be within 152 cm (5 ft) of the rear of the system and properly secured.
- Typical cylinder provides about 12.7 kg (28 lb) usable liquid CO2; at 130 g/min optimal flow it lasts just over 90 minutes.
- Banked cylinder configuration is preferred.
- Do not use helium head-pressure CO2 cylinders (retention time variation).
- Keep laboratory near 19 to 22 °C (66 to 72 °F) and warm cold-stored cylinders to ambient to avoid low inlet pressure.
The Prep SFC 150 MGM is available only as a 220-volt configuration using 6-20P plugs. All components require a dedicated, earthed power source with accessible receptacles sharing a common ground; extension cords must never be used. The customer must provide four 20-A, 220-V duplex sockets, at least four of which are used by the system depending on options. Installation over-voltage category II applies, and a line conditioner or UPS is recommended for long-term input voltage stability.
- System voltage: 220 V only, 6-20P plugs.
- Customer must provide four 20-A, 220-V duplex sockets; at least four used by the system.
- Never use an extension cord.
- All receptacles must share a common earthed ground.
- Over-voltage installation category II required.
- Optional valves each include a power supply requiring a receptacle on the common earthed source.
- Component power table: ABPR 220 VA; CHILL 1150 W at 115 V / 2395 W at 230 V; PDA and TUV detectors 185 VA each; FM1 9.0 VA; HE 462 W; MSI 132 W at 110 V / 176 W at 220 V; P1 220 VA; P2 176 W at 110 V / 352 W at 220 V; PFS 220 VA; TC 132 W at 110 V / 176 W at 220 V.
The laboratory must comply with pollution degree 2, have relative humidity below 80% noncondensing, and avoid excessive dust. Ambient temperature must be 15 to 28 °C (59 to 82 °F), with an optimum of 19 to 22 °C (66 to 72 °F) and short-term variations no more than 2 °C (3.6 °F) per 1.5 hours. Air flow from HVAC diffusers must not be directed at the system; the site must be away from heavy vibration sources, strong magnetic fields (NMR, magnetic sector MS), and RF emitters. The customer must provide suitable CO2 detectors with power and safety equipment.
- Pollution degree 2.
- Relative humidity <80%, noncondensing.
- Ambient temperature 15 to 28 °C (59 to 82 °F); optimum 19 to 22 °C (66 to 72 °F).
- Short-term thermal variation ≤2 °C (3.6 °F) per 1.5 hours.
- Do not direct HVAC diffuser airflow onto the system.
- Avoid heavy machines (compressors, generators), NMR/magnetic sector MS fields, and RF sources such as mobile phones and RF-linked alarms.
- Customer must provide CO2 detector(s), power sources, and warning strobes.
Dedicated waste containers capture waste from the manual back-pressure regulator (10-L SFC waste bottle with liner), the collection container waste manifold (20-L SFC waste bottle with liner), and the GLS drain, shelf unit tees, and 2545 vent valve port 3 (2-L SFC gas/liquid separator waste bottle). Waste containers are positioned below the bench top, and the system must be level for proper drainage and leak control. The collection cabinet provides a 3-inch vent for fume-hood exhaust to the outside; the active exhaust vent must provide a minimum vacuum of 2 mbar (0.03 psi) below atmospheric pressure.
- 10-L waste bottle with liner for MBPR waste.
- 20-L waste bottle with liner for collection container waste manifold.
- 2-L SFC gas/liquid separator waste bottle for GLS drain, shelf unit tees, and 2545 vent valve port 3.
- Position waste containers below the bench top.
- System must be level for drainage and leak control.
- Collection cabinet vent: 3-inch (7.6 cm) port for flexible ducting.
- Active exhaust vent minimum vacuum: 2 mbar (0.03 psi) below atmospheric.
- Exhaust venting must comply with local safety and environmental regulations; ANSI/AIHA Z9.2-2001 provides guidance.
The Waters service engineer uses test samples supplied with the system; if received separately, the customer must make them available at installation or the installation may be delayed and costs may be charged. The customer must supply CO2 at 99.97% minimum purity, CO2 detector(s), 4 L HPLC-grade methanol, a methanol wash bottle, three 100-mL volumetric flasks, three 250-mL bottles, a 50-mL graduated cylinder, a funnel, flexible ducting for the 7.6-cm (3.0-inch) vent port, nitrile gloves, lint-free tissue, and the Waters-supplied test samples.
- Provide Waters-supplied test samples at installation.
- CO2 supply: 99.97% pure minimum.
- 4-L HPLC-grade methanol plus methanol wash bottle.
- Three 100-mL volumetric flasks and three 250-mL bottles.
- 50-mL graduated cylinder and transfer funnel.
- Flexible ducting for 7.6-cm (3.0-inch) vent port.
- Nitrile gloves and lint-free tissue.
- Supplied glassware must never have been washed with detergent or in facilities with detergent residue.
Selection of a ChromScope Data System is required; contact a Waters sales representative for details on appropriate ChromScope data products. The Release Notes must be consulted for known and fixed issues, installation, configuration, and requalification/revalidation recommendations.
- ChromScope Data System required.
- Consult Release Notes for restrictions and requalification/revalidation recommendations.
Key Integration, Operating & Safety Requirements
| Specification / Condition | Engineering Implication | Applies To |
|---|---|---|
| The Prep SFC 150 MGM system is available only as a 220-volt configuration using 6-20P plugs. p.16 ↗ | Site electrical supply must be 220 V with 6-20P compatible receptacles; no 115 V variant exists. | Whole Prep SFC 150 MGM system |
| The customer must have four 20-A, 220-V duplex sockets available; depending on options, at least four sockets are used by the system. p.17 ↗ | Plan at least four dedicated 20-A/220-V circuits on a common earthed ground; optional valves require additional receptacles. | Whole system |
| Never use an extension cord to connect the instrument to an AC power source. p.16 ↗ | Receptacles must be within reach of component power cords; relocate equipment rather than extend with cords. | All system components |
| The laboratory environment must comply with installation (over-voltage) category II and pollution degree 2. p.16 ↗ | Verify site electrical installation category and cleanliness before installation. | Whole system |
| CO2 supply must be liquid, 99.97% pure (food-grade) or better, delivered at a minimum of 55 bar. p.15 ↗ | Select a dip-tube cylinder or in-house distribution system rated for at least 55 bar; dewars and low-pressure cylinders are not acceptable. | Whole system |
| A typical CO2 cylinder provides about 12.7 kg (28 lb) of usable liquid CO2; at the optimal flow rate of 130 g/min it lasts just over 90 minutes. p.15 ↗ | Plan cylinder banking or in-house distribution for runs longer than about 90 minutes. | Whole system |
| Do not use helium head-pressure CO2 cylinders. p.15 ↗ | Helium head pressure causes retention time variation; specify non-helium-pressurized CO2 supply. | Whole system |
| The CO2 cylinder must be within 152 cm (5 ft) of the rear of the system and properly secured in a fixed position. p.15 ↗ | Locate and restrain the cylinder within this distance during bench layout. | Cylinder-based CO2 supply |
| The Julabo chiller must be within 1 m (39.4 inches) of the CO2 pump. p.13 ↗ | Chiller placement is constrained by tubing length to P1 (CO2 pump). | CHILL and P1 |
| Allow at least 15.2 cm (6.0 inches) between the collection cabinet and the shelf system. p.10 ↗ | Bench layout must reserve this gap for access and tubing routing. | PCC and SS |
| Provide at least 152 cm (5 ft) of vertical clearance above the laboratory bench and 25.4 cm (10 inches) rear clearance for system components. p.12 ↗ | Bench location must be clear of overhead obstructions and have rear access space. | Whole system |
| Ambient temperature must be 15 to 28 °C (59 to 82 °F); optimum is 19 to 22 °C (66 to 72 °F); short-term variation must not exceed 2 °C (3.6 °F) per 1.5 hours. p.19 ↗ | HVAC must maintain tight temperature stability to avoid compromised performance and instrument failure. | Whole system |
| Relative humidity must be lower than 80%, noncondensing. p.19 ↗ | Dehumidification may be required in humid laboratories. | Whole system |
| The active exhaust vent must provide a minimum vacuum of 2 mbar (0.03 psi) below atmospheric pressure. p.21 ↗ | Customer-supplied exhaust system must be verified to meet this vacuum before installation. | Collection cabinet exhaust |
| The collection cabinet provides a 3-inch (7.6 cm) vent for fume-hood exhaust to the outside. p.22 ↗ | Supply flexible ducting compatible with the 7.6-cm vent port. | PCC |
| The system must be level to maintain proper drainage and leak control. p.21 ↗ | Level the bench/floor installation before connecting waste lines. | Whole system |
| Storage conditions before installation: 0 to 40 °C (32 to 104 °F), humidity <80% noncondensing, unopened shipping crates. p.9 ↗ | Storage area must meet these limits until the Waters engineer installs the system. | Shipping crates |
| Large crate dimensions: 123.2 cm W x 106.6 cm D x 158.8 cm H (48.5 x 42 x 62.5 inches); small crate: 114.3 cm W x 78.7 cm D x 77.5 cm H (45 x 31 x 30.5 inches). p.8 ↗ | Verify doorways, corridors, elevators, and staircases can accommodate the largest crate or unboxed component. | Shipping containers |
| Heaviest listed component is the Julabo chiller at 48.2 kg (106 lb); P2 is 39.5 kg (87 lb), P1 is 38.1 kg (84 lb), and PCC is 34 kg (75 lb). p.12 ↗ | Bench and lifting plan must support these point loads; use appropriate personnel or lifting equipment. | CHILL, P2, P1, PCC |
| Use HPLC-grade solvents; have 4 L methanol, ultra-pure water, and ethylene glycol available for installation. p.14 ↗ | Procure solvents and contamination-free glassware before the installation date. | Whole system |