Selection
The chiller is rated for an operating temperature range of -20 to 100 °C, which defines the process window it can serve.
Confirms whether the unit covers the required process temperatures before selection.
Source
“Operating temperature range -20...100 °C”
Performance
Cooling capacity drops from 21 kW at 0 °C to 7.5 kW at -20 °C, so low-temperature duty needs a larger unit or derating check.
Prevents undersizing when the process runs near the cold end of the range.
Source
“at -20°C 7,5 kW”
Installation
The unit requires a 400 V three-phase 50 Hz supply, so site power must be verified before installation.
Determines electrical infrastructure and whether a suitable three-phase feed is available.
Source
“Power supply (3 Phase) 400V 3~ 50Hz”
Installation
Three-phase devices below 63 A are delivered with cable but without a plug, so the customer must provide the final connection.
Affects electrical installation planning and the need to procure a suitable plug or isolator.
Source
“Three-phase devices with current consumption less than 63A --> with cable, without plug”
Installation
Voltage and frequency tolerances are ±5% and ±2% but must not be combined in opposite directions, so supply quality must be checked.
Avoids invalid supply conditions that could damage the compressor or void compliance.
Source
“Voltage + / - 5% with a simultaneous frequency tolerance of + / - 2%”
Installation
The unit is IP20, so it must be installed in a dry indoor location protected from water and dust ingress.
Restricts installation environment and enclosure requirements.
Source
“Degree of Protection IP20”
Installation
Ambient temperature must stay between 5 and 40 °C, and cooling capacity may fall above 20 °C room temperature.
Guides room ventilation and placement to avoid capacity loss or overheating.
Source
“max. ambient temperature 40 °C”
Installation
The unit is air-cooled and CFC/HCFC-free with refrigerant R-449A (GHS H280), so ventilation and refrigerant handling rules apply.
Informs room ventilation, leak response and service safety planning.
Source
“Refrigerant (ASHRAE, GHS) R-449A (A1, H280)”
Installation
The pump connection is G1 1/4 male, so mating hoses and fittings must match this thread.
Ensures correct hydraulic connection hardware is ordered and installed.
Source
“Pump connection G1 1/4 male”
Operation
The pump delivers 210 l/min at zero head but only 31 l/min at 4.5 bar, so system pressure drop must be matched to the pump curve.
Prevents selecting a unit whose flow collapses under the actual circuit resistance.
Source
“max. delivery 210 l/min”
Operation
Minimum filling capacity is 14 l and expansion volume is 39 l, so the external loop volume must be considered for proper operation.
Avoids underfilling or overflow issues in the closed external circuit.
Source
“min. filling capacity 14 l”
Safety
The unit has adjustable overtemperature protection per DIN 12876 and safety classification III/FL, so it can be set to protect the process.
Supports safe operation and compliance with laboratory chiller safety requirements.
Source
“With adjustable overtemperature protection according to DIN 12876.”
Compliance
The equipment is EMC Class A Group 1, so it may cause radio interference in residential areas and needs appropriate installation.
Affects placement and EMC planning, especially near sensitive electronics.
Source
“Classification (disturbance) to EN55011: Class A, Group 1”
Installation
Overall dimensions are 905x2172x1900 mm and space requirements must be respected, so the installation footprint must be planned.
Ensures sufficient floor space and access for installation and service.
Source
“Overall dimensions WxDxH ** 905x2172x1900 mm”