Operating Instructions — C-VLR 401 (BA 886-NL, NL)
Technical Reference Summary
Covered Models & Document Scope
C-VLR 401, C-VLR 501 and C-VLR 651 two-shaft dry-running claw vacuum pumps. Standard version (CD) for dry, non-explosive, non-flammable, non-aggressive, non-toxic gases and gas-air mixtures; version 'XD' with corrosion-resistant coating for moist gases/water vapour. Accessories include suction filter (paper or polyester). Document BA 886-NL, version 1.0, 25-05-2023.
Section-by-Section Technical Breakdown
Describes the C-VLR 401/501/651 as two-shaft dry-running claw vacuum pumps with non-contacting claw rotors synchronised by oil-lubricated gears. The gearbox and compression chamber are separated by special seals; the suction side has a connection flange with integrated non-return valve and mesh filter, the discharge side an exhaust silencer. An insulating hood and fan provide cooling; the fan is driven via a coupling by a standard three-phase motor mounted on the flange.
- Two-shaft claw principle, dry and contactless running
- Integrated non-return valve prevents venting of the evacuated system after shutdown
- Vacuum relief valve integrated in the machine
- Suction air cleaned by mesh filter
- Cooling air drawn between compressor and motor hood by drum fan
- Standard three-phase motor flange-mounted and coupled to fan
Defines continuous operation between 700 mbar (abs.) and an inlet pressure of 200 mbar (abs.). For closed systems the volume to be evacuated must not exceed 2% of the nominal pumping capacity. Free-air pumping capacities at 50 Hz are 380 m³/h (VLR 401), 495 m³/h (VLR 501) and 600 m³/h (VLR 651). Increased switching frequency or high ambient/suction temperatures can exceed motor winding and bearing temperature limits.
- Continuous operation range: 700 mbar (abs.) to 200 mbar (abs.) inlet pressure
- Closed-system volume ≤ 2% of nominal pumping capacity
- Pumping capacity at 50 Hz: 380 / 495 / 600 m³/h for 401 / 501 / 651
- XD version suitable for moist gases (water vapour)
- Consult manufacturer for ~10 starts per hour or elevated temperatures
- Outdoor installation requires weather protection (e.g. protective roof)
The machine can be installed on a firm floor without anchoring; on a substructure elastic buffer elements are recommended. Piping must be connected without excessive force or torque; hand-tighten only and use flexible connections if needed. The discharge opening must not be closed or restricted; maximum permissible back pressure is +50 mbar. Remove blind plugs before connecting, avoid liquid accumulation in the exhaust line, and check exhaust lines regularly for contamination.
- No anchoring required on firm floor; elastic buffers recommended on substructure
- Hand-tighten piping only; use flexible connections to avoid stress
- Maximum permissible back pressure +50 mbar
- Do not install shut-off devices in the discharge line
- Remove blind plugs from suction and discharge before connection
- Avoid liquid accumulation in the exhaust line
- Too narrow or too long suction line reduces pumping capacity
Electrical installation must be performed by a qualified electrician according to EN 60204. The operator must provide a main switch and a motor protection switch. Motors comply with DIN EN 60034, protection IP 55 and insulation class F. Direct-on-line starting is not permitted for AC motors above 1.7 kVA apparent power, three-phase motors above 5.2 kVA, or motors with starting currents above 60 A; star-delta, soft starter or frequency inverter must be used. Permissible supply tolerances are ±5% voltage and ±2% frequency.
- Motor protection switch and main switch to be installed by operator
- Motors: IP 55, insulation class F, DIN EN 60034
- Direct start limit: >1.7 kVA AC, >5.2 kVA three-phase, or >60 A starting current
- Use star-delta, soft starter or frequency inverter above these limits
- Voltage tolerance ±5%, frequency tolerance ±2%
- Check motor rotation direction against arrow on motor flange
- Connection diagram inside motor terminal box (not applicable to plug connector version)
Before commissioning, check for transport or assembly damage and verify installation. Check rotation direction against the arrow on the motor flange. During operation check oil level at the sight glass and top up if necessary. For XD version, drain condensate from the silencer depending on condensation.
- Check for transport/assembly damage before commissioning
- Verify motor rotation direction matches arrow
- Check oil level at sight glass and top up as needed
- Drain condensate from silencer on XD version depending on condensation
Lists maintenance intervals and activities. Monthly: check pipes and screw connections for leaks and tightness, check terminal box and cable entries, clean ventilation slots and motor cooling fins, check oil level, check/clean/replace air filter, clean mesh filter in suction connection, drain condensate from silencer (XD). Oil change every 20,000 h (only with Elmo Rietschle approved oils; extreme conditions can reduce oil life to 5,000 h). Check coupling wear at least annually. General overhaul at 40,000 h by Elmo Rietschle Service.
- Monthly: leak check on pipes and screw connections
- Monthly: clean ventilation slots and motor cooling fins
- Monthly: check oil level (Chapter 7.5.1)
- Monthly: clean mesh filter in suction connection (Chapter 7.4)
- Oil change interval 20,000 h only with approved oils; can drop to 5,000 h under extreme conditions
- Check coupling wear at least once per year
- General overhaul at 40,000 h by Elmo Rietschle Service
Oil change must be performed with the machine warm (approx. 40 °C) and well ventilated. Use ISO VG 150 oil according to DIN ISO 3448; recommended oils are GEAR-LUBE 150 and ECO-GEAR-LUBE 150. The mesh filter must be cleaned or replaced monthly; the suction filter cartridge (accessory) must be cleaned monthly and replaced every six months. Tightening torque for suction flange screws is 10 Nm.
- Oil viscosity: ISO VG 150 per DIN ISO 3448
- Recommended oils: GEAR-LUBE 150, ECO-GEAR-LUBE 150
- Oil change with machine warm (approx. 40 °C)
- Mesh filter: clean monthly or replace; suction flange screws 10 Nm
- Suction filter cartridge (accessory): clean monthly, replace every 6 months
Describes removal and refitting of the motor and coupling. The motor is suspended by lifting eyes or round slings; the motor flange screws are loosened and the motor with coupling half pulled axially from the fan housing. Check the coupling gear rim and fan, replace if damaged or worn. Refit and tighten motor flange screws to 84 Nm.
- Motor flange screw tightening torque: 84 Nm
- Check coupling gear rim for damage/wear and replace if necessary
- Check fan and replace if necessary
Only original or manufacturer-approved spare parts may be used. Spare parts are listed in document E886. Service kits containing all wear parts and gaskets are available. Identified spare parts include coupling star ZS1183380 and mesh filter ZS1114498. Approved oils: GEAR LUBE 150 (1 l dose 7201706000, 200 l drum 7201656000) and ECO GEAR LUBE 150 (1 l dose 7203850000).
- Coupling star: ZS1183380
- Mesh filter: ZS1114498
- GEAR LUBE 150: 1 l 7201706000, 200 l 7201656000
- ECO GEAR LUBE 150: 1 l 7203850000
- Spare parts list: E886
Technical data are provided on the data sheet D 886 and on the nameplate. The nameplate includes type/mechanical variant, serial number, year of construction, data matrix barcode, article number, speed 50/60 Hz, motor power 50/60 Hz, operating mode, pumping capacity 50/60 Hz and ultimate pressure (abs.) 50/60 Hz.
- Refer to data sheet D 886 for technical data and curves
- Nameplate includes speed, motor power, operating mode, pumping capacity and ultimate pressure for 50 and 60 Hz
Key Integration, Operating & Safety Requirements
| Specification / Condition | Engineering Implication | Applies To |
|---|---|---|
| Permissible ambient and suction temperature range is 5 to 40 °C. p.8 ↗ | Operation outside this range requires consultation with the manufacturer; ensure installation environment stays within limits. | C-VLR 401/501/651 all versions |
| Maximum permissible back pressure at discharge is +50 mbar. p.8 ↗ | Do not install shut-off devices or restrictions in the discharge line; higher back pressure requires consultation. | C-VLR 401/501/651 all versions |
| Continuous operation is permitted between 700 mbar (abs.) and 200 mbar (abs.) inlet pressure. p.16 ↗ | Select pump for applications within this inlet pressure range; operation outside may require manufacturer consultation. | C-VLR 401/501/651 |
| For closed systems, the volume to be evacuated must not exceed 2% of the nominal pumping capacity. p.16 ↗ | Size vacuum reservoir or connected volume accordingly to avoid overheating or overload. | C-VLR 401/501/651 |
| Pumping capacity at 50 Hz free suction: 380 m³/h (VLR 401), 495 m³/h (VLR 501), 600 m³/h (VLR 651). p.16 ↗ | Use these values for preliminary sizing; refer to data sheet D 886 for capacity vs. inlet pressure curves. | C-VLR 401, 501, 651 |
| Direct-on-line starting is not permitted for AC motors >1.7 kVA apparent power, three-phase motors >5.2 kVA, or motors with starting current >60 A. p.19 ↗ | Use star-delta starter, soft starter or frequency inverter for larger motors. | C-VLR 401/501/651 with corresponding motor |
| Permissible supply voltage deviation is ±5% and frequency deviation ±2% from nominal. p.19 ↗ | Verify site power quality before connection; out-of-tolerance supply can reduce performance or damage motor. | C-VLR 401/501/651 |
| Motor protection: IP 55, insulation class F, according to DIN EN 60034. p.19 ↗ | Suitable for industrial environments; ensure cable entries and terminal box are properly sealed to maintain IP 55. | C-VLR 401/501/651 standard motors |
| Oil change interval is 20,000 operating hours only when using Elmo Rietschle approved oils; extreme conditions can reduce oil life to 5,000 hours. p.23 ↗ | Use only GEAR-LUBE 150 or ECO-GEAR-LUBE 150 to maintain 20,000 h interval; adjust maintenance schedule for severe duty. | C-VLR 401/501/651 |
| Oil viscosity must be ISO VG 150 according to DIN ISO 3448. p.25 ↗ | Select only approved ISO VG 150 oils; mixing or using other viscosities may affect lubrication and warranty. | C-VLR 401/501/651 |
| Tightening torque for suction flange screws is 10 Nm. p.27 ↗ | Observe torque when reassembling mesh filter and suction flange to ensure leak-free connection. | C-VLR 401/501/651 |
| Tightening torque for motor flange screws is 84 Nm. p.29 ↗ | Use torque wrench when refitting motor after coupling maintenance. | C-VLR 401/501/651 |
| Storage temperature range: -20 °C to +70 °C; relative humidity max. 80%; storage in dust-free, dry, vibration-free, sun-protected environment; storage >6 months should be avoided. p.13 ↗ | Plan spare pump storage accordingly; seal openings airtight. | C-VLR 401/501/651 |
| Surface temperatures can exceed 70 °C during operation. p.23 ↗ | Provide touch protection or ensure inaccessible during operation; allow cool-down before maintenance. | C-VLR 401/501/651 |
| Increased switching frequency of approximately 10 times per hour or elevated ambient/suction temperatures can exceed motor winding and bearing temperature limits. p.16 ↗ | Consult manufacturer for such duty; may require larger motor or modified operation. | C-VLR 401/501/651 |
| The XD version has a corrosion-resistant coating and is suitable for transporting moist gases (water vapour). p.16 ↗ | Select XD version for humid or water-vapour applications; standard version must not be used with water vapour. | C-VLR 401/501/651 XD |
| Suction filter cartridge (accessory) must be replaced every six months regardless of cleaning. p.27 ↗ | Include filter replacement in semi-annual maintenance schedule. | C-VLR 401/501/651 with suction filter accessory |
| General overhaul of the vacuum pump (replacement of wear and sealing parts) is due at 40,000 operating hours and must be performed by Elmo Rietschle Service. p.24 ↗ | Plan major service at 40,000 h to maintain reliability. | C-VLR 401/501/651 |
Faults & Troubleshooting
| Code / Symptom | Possible Cause | Remedy | Note |
|---|---|---|---|
| Machine wordt uitgeschakeld door motorbeveiligingsschakelaar p.31 ↗ | Netspanning/frequentie komt niet overeen met de motorgegevens | Inspectie door gekwalificeerde elektricien | Hoofdstuk 5.5 |
| Machine wordt uitgeschakeld door motorbeveiligingsschakelaar p.31 ↗ | De aansluiting op het motorklemmenbord is niet juist | Inspectie door gekwalificeerde elektricien | Hoofdstuk 5.5 |
| Machine wordt uitgeschakeld door motorbeveiligingsschakelaar p.31 ↗ | Motorbeveiligingsschakelaar is niet goed ingesteld | Inspectie door gekwalificeerde elektricien | Hoofdstuk 5.5 |
| De motorbeveiligingsschakelaar schakelt te snel uit p.31 ↗ | Kortstondige overstroom bij het opstarten | Gebruik van een motorbeveiligingsschakelaar met overbelastingsafhankelijke uitschakelvertraging die rekening houdt met de kortstondige overstroom bij het opstarten (versie met kortsluit- en overbelastingsbeveiliging volgens VDE 0660 deel 102 of IEC/EN 60947-4-1) | |
| Zuigkracht is onvoldoende p.31 ↗ | Luchtfilter is vuil | Luchtfilter reinigen/vernieuwen | Hoofdstuk 7.6, Hoofdstuk 7.9 |
| Zuigkracht is onvoldoende p.31 ↗ | Aanzuigleiding is te lang of te smal | Controleer de slang of pijpleiding | Hoofdstuk 5.3 |
| Zuigkracht is onvoldoende p.31 ↗ | Lekkage op de machine of in het systeem | Controleer leidingen en schroefverbindingen op lekken en dichtheid | Hoofdstuk 5.3 |
| Einddruk (max. vacuüm) wordt niet bereikt p.31 ↗ | Lekkage op de machine of in het systeem | Controleer leidingen en schroefverbindingen op lekken en dichtheid | Hoofdstuk 5.3 |
| Einddruk (max. vacuüm) wordt niet bereikt p.31 ↗ | Luchtfilter is vuil | Luchtfilter reinigen/vernieuwen | Hoofdstuk 7.6, Hoofdstuk 7.9 |
| Machine wordt te heet p.31 ↗ | Omgevingstemperatuur of inlaattemperatuur is te hoog | Houd rekening met het beoogde gebruik | Hoofdstuk 2.4 |
| Machine wordt te heet p.31 ↗ | Koelluchtstroom wordt belemmerd | Controleer de omgevingsomstandigheden | Hoofdstuk 5.1 |
| Machine wordt te heet p.31 ↗ | Koelluchtstroom wordt belemmerd | Ventilatiesleuven reinigen | Hoofdstuk 7.4 |
| Machine produceert abnormaal geluid p.31 ↗ | Afzettingen op de roterende zuigers | Reinig de werkkamer en de roterende zuigers | Elmo Rietschle Service |